Standard installation includes
- Installation of a new fuse group in the electrical panel
- Cabling (5g4mm2) between charging station and electrical panel. Max. 10 meters cable
- Routing above ceiling, outside on wall or in ground (if customer has exposed 40cm depth)
- Drilling of up to 2 holes in wall or ceiling
- Assembly and testing of the charging station
- Installation of charge box for 11 kW charging (16A)
- Driving to bridged islands
- Cable burial, removal of tiles and stones must be prepared in advance
- Upgrade to 22 kW requires that the house has sufficient power available
- Additional work will be billed directly by the installer
- Replacement of existing charger, requires that the existing installation can be reused
- Max charging power depends on available amps at the address and the car's charging speed